Development of Alarm System link Drawing for Operation Support for APR1400 Digital Main Control Room

Creators

  • 1. KHNP CRI, Daejeon (Korea, Republic of)

Description

Digitalized MMI(Man-Machine Interface) including Digital Main Control Room(MCR) and digital I and C system was being applied for SKN 3 and 4 Nuclear Power Plant(NPP) and subsequent APR1400 NPP type. But, operators can not easily find instrument for alarm immediately. Therefore, Alarm system is required to easily find instrument for Alarm. For this implementation, we will plan system design considering design feature without affecting network load and CPU load. We have developed Alarm system link drawing for digital MCR. Operators of the digitalized MCR navigates from their consoles to the drawings related to the plant alarms and their instruments or the operation status. Such method gives cognitive load to the operators having to travel to different locations in finding the related information. Screen Sharing System, which is the fundamental technique for Drawing Interconnection Alarm System is close to completion, and it should be functionally tested and verified by the human factor engineering. For the actual application to the operating plants, the drawings to be interconnected to the alarms and the opinions from the operators/maintenance departments for designating alarm number should be surveyed, Also, another function that allows the access to the alarm related drawings not only from the MCR but also from the other offices

Part of:
Proceedings of the KNS 2016 Autumn Meeting

Additional details

Publishing Information

Publisher
KNS
Imprint Place
Daejeon (Korea, Republic of)
Imprint Title
Proceedings of the KNS 2016 Autumn Meeting
Imprint Pagination
[1 CD-ROM]
Journal Page Range
[3 p.]

Conference

Title
2016 Autumn Meeting of the KNS
Dates
26-28 Oct 2016
Place
Kyungju (Korea, Republic of)

INIS

Country of Publication
Korea, Republic of
Country of Input or Organization
Korea, Republic of
INIS RN
48067699
Subject category
S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
Resource subtype / Literary indicator
Conference, Non-conventional Literature
Descriptors DEI
ALARM SYSTEMS; CONTROL ROOMS; INTERFACES; MAN-MACHINE SYSTEMS; PWR TYPE REACTORS; REACTOR OPERATION; USES; VERIFICATION
Descriptors DEC
ENRICHED URANIUM REACTORS; OPERATION; POWER REACTORS; REACTOR LIFE CYCLE; REACTORS; THERMAL REACTORS; WATER COOLED REACTORS; WATER MODERATED REACTORS

Optional Information

Notes
2 refs, 4 figs