Published February 2019 | Version v1
Journal article

Analysis of R Bank Frequent Action Problem in Yangjiang Nuclear Power Plant

  • 1. State Key Laboratory of Nuclear Power Safety Monitoring Technology and Equipment, China Nuclear Power Engineering Co. Ltd., Shenzhen (China)

Description

In the 2nd and 3rd nuclear fuel cycles of Unit 1, Unit 2 and Unit 3 in Yangjiang Nuclear Power Plant, R bank acts frequently, seriously affecting the safety with operation of the unit. In this paper, the logic control principle of R bank and the loading of core are analyzed, and the transfer function of first-order inertia, lead lag and differential link is converted into difference equation. The theoretical calculation is carried out before the parameter is modified, and the temperature ± 4℃ disturbance simulation test upon 87% FP power platform is carried out on the plant simulator. The test results show that the modified parameters are correct and can solve the frequent action problem of R bank. After the modification of the parameters for Unit 2, the R bank acts normally, and R bank action frequency is about 1 time per 2 days. (authors)

Additional details

Identifiers

Publishing Information

Journal Title
Nuclear Power Engineering
Journal Volume
40
Journal Issue
1
Journal Page Range
p. 97-100
ISSN
0258-0926

Optional Information

Notes
5 figs., 4 tabs., 3 refs.; http://dx.doi.org/10.13832/j.jnpe.2019.01.0097