Analysis on optimization of the critical path for civil construction period of Fangjiashan nuclear island constructed under EPC mode
Description
Based on the actual situation of nuclear island civil construction in Fangjiashan nuclear power plant and combined with the arrangement of the construction schedule, the analysis on optimization of the critical path for civil construction period is conducted. The result shows that on the premise of not increasing the contract price and the total engineering cost based on the original 57-month construction period, the construction period can be shorten to 21 month through strengthening the schedule control, keeping the critical work in a reasonable duration and rearranging the link between programmers. In addition, in view of the economic analysis, if we increase the mechanical engagement and adopt special method, the 2-month construction period can be even shortened to 20 months. (authors)
Additional details
Publishing Information
- Journal Title
- China Nuclear Power
- Journal Volume
- 4
- Journal Issue
- 3
- Journal Page Range
- p. 226-235
- ISSN
- 1674-1617
INIS
- Country of Publication
- China
- Country of Input or Organization
- China
- INIS RN
- 45059100
- Subject category
- S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
- Descriptors DEI
- AUGMENTATION; CHINA; CIVIL ENGINEERING; CONSTRUCTION; CONTRACTS; COST; ECONOMIC ANALYSIS; ENGINEERING; NUCLEAR POWER PLANTS; OPTIMIZATION; PERT METHOD; PWR TYPE REACTORS; SCHEDULES
- Descriptors DEC
- ASIA; ECONOMICS; ENGINEERING; ENRICHED URANIUM REACTORS; NUCLEAR FACILITIES; POWER PLANTS; POWER REACTORS; REACTORS; THERMAL POWER PLANTS; THERMAL REACTORS; WATER COOLED REACTORS; WATER MODERATED REACTORS
Optional Information
- Notes
- 9 figs., 1 tabs.