Published 2002 | Version v1
Report Open

Nuclear power plant A-1 decommissioning

  • 1. SE-VYZ o.z., Slovak Electric, Plc, Nuclear Installations Decommissioning, Radwaste and Spent Fuel Management, Jaslovske Bohunice (Slovakia)

Description

In the presentation, some information concerning the historical background of NPP A-1 in Jaslovske Bohunice, Slovakia is given. The main technical parameters used during production activities concerning the decommissioning of the NPP A-1 to a first stage (i.e. to obtain radiologically safe stage) are solved together with the main contractor, Nuclear Power Plant Research Institute, Trnava, according to an approved project by the Slovak Government and Nuclear Authorities. The technological schemes for the radioactive waste treatment at SE-VYZ o.z. and their main technical parameters are shown as well. (author)

Files

33052281.pdf

Files (84.6 kB)

Name Size Download all
md5:b0efc9e353c93833faed192dc8608fc2
84.6 kB Preview Download
Part of:
International conference on safe decommissioning for nuclear activities: Assuring the safe termination of practices involving radioactive materials. Contributed papers

Additional details

Publishing Information

Imprint Title
International conference on safe decommissioning for nuclear activities: Assuring the safe termination of practices involving radioactive materials. Contributed papers
Imprint Pagination
408 p.
Journal Page Range
p. 154-157
Report number
IAEA-CN--93

Conference

Title
Assuring the safe termination of practices involving radioactive materials
Acronym
International conference on safe decommissioning for nuclear activities
Dates
14-18 Oct 2002
Place
Berlin (Germany)

INIS

Country of Publication
International Atomic Energy Agency (IAEA)
Country of Input or Organization
International Atomic Energy Agency (IAEA)
INIS RN
33052281
Subject category
S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
Resource subtype / Literary indicator
Conference
Descriptors DEI
BOHUNICE A-1 REACTOR; RADIOACTIVE WASTE MANAGEMENT; REACTOR DECOMMISSIONING; REACTOR SHUTDOWN; SAFETY
Descriptors DEC
CARBON DIOXIDE COOLED REACTORS; DECOMMISSIONING; GAS COOLED REACTORS; HEAVY WATER MODERATED REACTORS; HWGCR TYPE REACTORS; MANAGEMENT; NATURAL URANIUM REACTORS; POWER REACTORS; REACTORS; SHUTDOWN; THERMAL REACTORS; WASTE MANAGEMENT

Optional Information

Contract/Grant/Project number
Project Decommissioning NPP A-1 Phase I
Secondary number(s)
CN--93[33]