Probabilistic safety analyses developments resurgence in Bulgaria-Kozloduy nuclear power plant example

  • 1. Risk engineering Plc, Sofia (Bulgaria)
  • 2. Institute for Nuclear Research and Nuclear Energy, Sofia (Bulgaria)
  • 3. Kozloduy NPP Plc, Kozloduy (Bulgaria)

Description

This paper presents some of the main technical features and insights of the Kozloduy nuclear power plant (NPP) units 5 and 6 probabilistic safety analysis (PSA) level 1. Probabilistic analyses and their applications in Bulgaria were given further impetus in recent years. More than 17 years after the first PSA study in Bulgaria in 1992 today probabilistic analyses receive increasing attention and application than ever before. The Bulgarian regulatory body (BNRA) is also interested in expanding their capability of reviewing and using PSA in plant safety assessments. In November 2008 within the framework of the program financed by European Union (PHARE), a project for assisting the BNRA in establishing the regulatory requirements on the base of PSA was completed. One of the objectives of this project was performance of the independent review of Kozloduy NPP units 5 and 6 PSA. This review was a new impulse for the authors to present in more details of Kozloduy NPP probabilistic assessment studies in the present paper.

Availability note (English)

Available from http://dx.doi.org/10.1016/j.nucengdes.2009.11.047

Additional details

Identifiers

DOI
10.1016/j.nucengdes.2009.11.047;
PII
S0029-5493(09)00641-4;

Publishing Information

Journal Title
Nuclear Engineering and Design
Journal Volume
240
Journal Issue
4
Journal Page Range
p. 880-885
ISSN
0029-5493
CODEN
NEDEAU