Re-validation of the equipment seismic qualification adequacy due to the change of required response spectra
Description
In cases where a new set of the floor response spectra curves are generated in the course of nuclear plant design, all safety related seismic category I system, structure and components shall be re-validated for their seismic design adequacy under the effect of the new response spectra requirement. This paper recommends a two-tier of screening process; floor response spectra is screened first, and followed by equipment screening. After this screening process is completed, only a limited number of the new response spectra and a small population of the Seismic Category I equipment would need to be considered for the re-validation. As such, the reduced scope of work can lead to a systematic and cost-effective method for re-validation of the existing equipment qualification results due to new RRS effects. (author)
Additional details
Publishing Information
- Publisher
- Elsevier
- Imprint Place
- Amsterdam (Netherlands)
- ISBN
- 0-444-81515-5
- Imprint Title
- Transactions of the 12th international conference on structural mechanics in reactor technology. Volume A: Supplement
- Imprint Pagination
- 261 p.
- Journal Page Range
- p. 219-223
Conference
- Title
- 12. international conference on structural mechanics in reactor technology
- Acronym
- SMiRT 12
- Dates
- 15-20 Aug 1993
- Place
- Stuttgart (Germany)
INIS
- Country of Publication
- Netherlands
- Country of Input or Organization
- International Atomic Energy Agency (IAEA)
- INIS RN
- 35091159
- Subject category
- S42: ENGINEERING; S22: GENERAL STUDIES OF NUCLEAR REACTORS;
- Resource subtype / Literary indicator
- Conference
- Descriptors DEI
- DESIGN; FLOORS; SEISMIC DETECTORS; SEISMIC EFFECTS; SEISMIC ISOLATION; SPECTRAL RESPONSE; VALIDATION
- Descriptors DEC
- MEASURING INSTRUMENTS; TESTING