Heysham 2, United Kingdom, 2000. Annex III. Description of Selected Open Phase Events

Creators

Description

On 30 Dec. 2000, Reactor 8 was manually tripped at 06:25 following a part failure of the blue phase circuit breaker, X890, in the 400 kV substation. The reactor was operating under reduced load conditions while on-load refuelling was in progress. Reactor 7 remained under steady full load conditions (671 MW).

Part of:
Impact of Open Phase Conditions on Electrical Power Systems of Nuclear Power Plants

Additional details

Publishing Information

Publisher
IAEA
Imprint Place
Vienna (International Atomic Energy Agency (IAEA))
ISBN
978-92-0-108516-0
Imprint Title
Impact of Open Phase Conditions on Electrical Power Systems of Nuclear Power Plants
Imprint Pagination
104 p.
Journal Issue
no. 91
Series
Safety Reports Series
Journal Page Range
p. 64
ISSN
1020-6450

Optional Information

Notes
This record replaces 48012254
Secondary number(s)
STI/PUB--1755