Five new beams were extracted from the cyclotron during two development runs, achieving two targets in the commissioning schedule: production of a beam at low magnetic field, and production of the 20th cyclotron beam. A carbon beam was produced and analyzed from the second ion source deck, completing its commissioning. The high energy tandem foil stripper was fully commissioned and is now available. (L.L.)