Short-term hydro generation scheduling of Xiluodu and Xiangjiaba cascade hydropower stations using improved binary-real coded bee colony optimization algorithm

Description

Highlights: • STHGS problem is decomposed into two parallel sub-problems of UC and ELD. • Binary coded BCO is used to solve UC sub-problem with 0–1 discrete variables. • Real coded BCO is used to solve ELD sub-problem with continuous variables. • Some heuristic repairing strategies are designed to handle various constraints. • The STHGS of Xiluodu and Xiangjiaba cascade stations is solved by IB-RBCO. - Abstract: Short-term hydro generation scheduling (STHGS) of cascade hydropower stations is a typical nonlinear mixed integer optimization problem to minimize the total water consumption while simultaneously meeting the grid requirements and other hydraulic and electrical constraints. In this paper, STHGS problem is decomposed into two parallel sub-problems of unit commitment (UC) and economic load dispatch (ELD), and the methodology of improved binary-real coded bee colony optimization (IB-RBCO) algorithm is proposed to solve them. Firstly, the improved binary coded BCO is used to solve the UC sub-problem with 0–1 discrete variables, and the heuristic repairing strategy for unit state constrains is applied to generate the feasible unit commitment schedule. Then, the improved real coded BCO is used to solve the ELD sub-problem with continuous variables, and an effective method is introduced to handle various unit operation constraints. Especially, the new updating strategy of DE/best/2/bin method with dynamic parameter control mechanism is applied to real coded BCO to improve the search ability of IB-RBCO. Finally, to verify the feasibility and effectiveness of the proposed IB-RBCO method, it is applied to solve the STHGS problem of Xiluodu and Xiangjiaba cascaded hydropower stations, and the simulating results are compared with other intelligence algorithms. The simulation results demonstrate that the proposed IB-RBCO method can get higher-quality solutions with less water consumption and shorter calculating time when facing the complex STHGS problem

Availability note (English)

Available from http://dx.doi.org/10.1016/j.enconman.2014.11.036

Additional details

Identifiers

DOI
10.1016/j.enconman.2014.11.036;
PII
S0196-8904(14)00993-5;

Publishing Information

Journal Title
Energy Conversion and Management
Journal Volume
91
Journal Issue
Complete
Journal Page Range
p. 19-31
ISSN
0196-8904
CODEN
ECMADL

INIS

Country of Publication
United Kingdom
Country of Input or Organization
International Atomic Energy Agency (IAEA)
INIS RN
46106522
Subject category
S29: ENERGY PLANNING, POLICY AND ECONOMY;
Descriptors DEI
ALGORITHMS; CONTROL SYSTEMS; ECONOMICS; HYDROELECTRIC POWER PLANTS; NONLINEAR PROBLEMS; OPERATION; OPTIMIZATION; SCHEDULES; WATER
Descriptors DEC
HYDROGEN COMPOUNDS; MATHEMATICAL LOGIC; OXYGEN COMPOUNDS; POWER PLANTS

Optional Information

Copyright
Copyright (c) 2014 Elsevier Science B.V., Amsterdam, The Netherlands, All rights reserved.