During a 1993 Outage at the Perry Nuclear Power Station, a condition report was issued which identified potential intersystem loss of water between the Emergency Closed Cooling Water System and the Nuclear Closed Cooling Water System during a design basis event. The review of this condition report indicated that if a SSE (safe shutdown earthquake) event were to occur during a design basis event components important to plant safety could potentially be adversely affected if non-seismic/non-safety portions of the Nuclear Closed Cooling Water System could not maintain pressure boundary integrity as a result of the seismic loadings. Presented in this paper are steps, criteria, and methodology used to demonstrate the seismic acceptability of the affected portion of the Nuclear Closed Cooling Water System Piping. Also discussed are the potential benefits and applicability of a recently developed EPRI non-safety, non-seismic operability procedure. This discussion includes the potential cost savings which could have arisen from application of this recently developed procedure

Additional details

Publishing Information

Publisher
American Society of Mechanical Engineers.
Imprint Place
New York, NY (United States)
ISBN
0-7918-1344-4
Imprint Title
International pressure vessels and piping codes and standards. Volume 2: Current perspectives; PVP-Volume 313-2
Imprint Pagination
505 p.
Journal Page Range
p. 325-330.

Conference

Title
Joint ASME/JSME pressure vessels and piping conference.
Dates
23-27 Jul 1995.
Place
Honolulu, HI (United States).

Optional Information

Secondary number(s)
CONF-950740--.