Planning of remotely handled dismantling of the reactor pressure vessel and its internals, based on the example of the Greifswald reactors

  • 1. Nukem GmbH, Alzenau (Germany)
  • 2. NUKEM Dresden GmbH (Germany)

Description

This paper concentrates on the representation of the technical concept worked out for remotely handled dismantling. (orig.)

Abstract (German)

Dieser Vortrag beschraenkt sich im wesentlichen auf die Darstellung des erarbeiteten technischen Konzeptes fuer die fernbediente Demontage. (orig.)
Part of:
2. decommissioning colloquium

Additional details

Additional titles

Original title (German)
Planung zur fernbedienten Demontage des RDB und seiner Einbauten am Beispiel der Greifswaelder Reaktoren

Publishing Information

Imprint Title
2. decommissioning colloquium
Imprint Pagination
210 p.
Journal Page Range
p. 31-37.

Conference

Title
Decommissioning and dismantling of the Greifswald nuclear plants.
Original Conference Title
2. Stillegungskolloquium: Stillegung und Abbau der Kernkraftwerke Greifswald
Acronym
2. decommissioning colloquium
Dates
19-20 Nov 1992.
Place
Hannover (Germany).

Optional Information

Notes
Imprint:2. Stillegungskolloquium.;Manuskripte bzw. Kurzfassungen der Vortraege. Tischvorlage.