Geotechnical Analysis Report for July 1999 - June 2000
Description
This Geotechnical Analysis Report (GAR) presents and interprets the geotechnical data from the underground excavations at the Waste Isolation Pilot Plant (WIPP). The data, which are obtained as part of a regular monitoring program, are used to characterize conditions, to compare actual performance to the design assumptions, and to evaluate and forecast the performance of the underground excavations during operations. GARs have been available to the public since 1983. During the Site and Preliminary Design Validation (SPDV) Program, the architect/engineer for the project produced these reports on a quarterly basis to document the geomechanical performance during and immediately after excavation of the underground facility. Since the completion of the construction phase of the project in 1987, the management and operating contractor for the facility has prepared these reports annually. This report describes the performance and condition of selected areas from July 1, 1999, to June 30, 2000. It is divided into ten chapters. The remainder of Chapter 1 provides background information on the WIPP, its mission, and the purpose and scope of the geomechanical monitoring program. Chapter 2 describes the local and regional geology of the WIPP site. Chapters 3 and 4 describe the geomechanical instrumentation located in the shafts and shaft stations, present the data collected by that instrumentation, and provide interpretation of these data. Chapters 5, 6, and 7 present the results of geomechanical monitoring in the three main portions of the WIPP underground facility (the access drifts, the Northern Experimental Area, and the Waste Disposal Area). Chapter 8 discusses the results of the Geoscience Program, which includes fracture mapping, borehole logging, and borehole observations. Chapter 9 provides an assessment of the hydrologic conditions near the Exhaust Shaft. Chapter 10 summarizes the results of the geomechanical monitoring and compares the current excavation performance to the design requirements
Availability note (English)
Available from INIS in electronic form; Also available from OSTI as DE00814862; PURL: https://www.osti.gov/servlets/purl/814862-TtExIU/native/
Files
Additional details
Identifiers
Publishing Information
- Imprint Pagination
- 113 p.
- Report number
- DOE/WIPP--01-3177/v.1
INIS
- Country of Publication
- United States
- Country of Input or Organization
- United States
- INIS RN
- 34087358
- Subject category
- S12: MANAGEMENT OF RADIOACTIVE WASTES, AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES;
- Descriptors DEI
- BOREHOLES; CONSTRUCTION; CONTRACTORS; DESIGN; EXCAVATION; FRACTURES; GEOLOGY; MONITORING; PERFORMANCE; RADIOACTIVE WASTE DISPOSAL; VALIDATION; WIPP
- Descriptors DEC
- CAVITIES; FAILURES; FUNCTIONAL MODELS; MANAGEMENT; NATIONAL ORGANIZATIONS; NUCLEAR FACILITIES; PILOT PLANTS; RADIOACTIVE WASTE FACILITIES; RADIOACTIVE WASTE MANAGEMENT; TESTING; UNDERGROUND FACILITIES; US DOE; US ORGANIZATIONS; WASTE DISPOSAL; WASTE MANAGEMENT
Optional Information
- Contract/Grant/Project number
- AC04-01AL66444
- Funding organization
- US Department of Energy (United States)