The initial criticality and nuclear commissioning test program at HANARO

  • 1. Korea Atomic Energy Research Institute, Dukjin-Dong 150, Yusung-Ku, Taejon, 305-353 (Korea, Republic of)

Description

The construction of the Korea Multipurpose Research Reactor - HANARO of 3MW, developed by Korea Atomic Energy Research Institute, was completed at the beginning of this year. The first fuel loading began on February 2 1995, and initial criticality was achieved on February 8, when the core had four 18-element assemblies and thirteen 36-element assemblies. The critical control rod position was 600.8 mm which represents excess reactivity of 0.71 $. Currently the nuclear commissioning test is on going under the zero power range. This paper describes the initial criticality approach of the HANARO, and its nuclear commissioning test program. (author)

Files

36023821.pdf

Files (317.2 kB)

Name Size Download all
md5:940c5c908650872f715f8857781f94ef
317.2 kB Preview Download
Part of:
IGORR-IV: Proceedings of the fourth meeting of the International Group On Research Reactors

Additional details

Publishing Information

Imprint Title
IGORR-IV: Proceedings of the fourth meeting of the International Group On Research Reactors
Imprint Pagination
426 p.
Journal Page Range
p. 39-48
Report number
CONF--9505218

Conference

Title
4. meeting of the International Group On Research Reactors
Dates
23-25 May 1995
Place
Gatlinburg, TN (United States)

Optional Information

Contract/Grant/Project number
Contract DE-AC05-84OR21400
Notes
4 refs, 6 figs
Secondary number(s)
INIS-XA-C--026