Financing Nuclear Projects. Case Study: Unit 2 Cernavoda NPP
- 1. Societatea Nationala 'Nuclearelectrica' S.A., 65 Polona, PO Box 22-102, RO-010494 Bucharest (RO)
- 2. Institute of Power Study and Design, Bd. Lacul Tei Nr.1, Bucharest (RO)
Description
The implementation of a Nuclear Power Plant (NPP) is a major undertaking for all entities involved, due to the necessity of planning work and coordination of the implementation process of the different fields of interest, starting with the governmental authorities and ending with the public. Having in view the specific investment costs (relatively high) for a NPP, finding an adequate financing structure is possible through an iterative process that involves first an assessment of the technical performances of the project and secondly, the mathematical modelling of the financing structure effects on the projects. In this respect, the paper will be focused on the main steps needed in order to promote an investment project in nuclear field, starting with the decision phase, providing the documentation requested by the local and international authorities to promote the project and ending with the negotiation of the contracts (commercial contract, financing contract, purchase contract, etc). The case study will be focused on the phases achieved in order to promote the Unit 2 NPP Cernavoda completion works project. (authors)
Availability note (English)
Available from author(s) or Romanian Nuclear Energy Association, AREN, Str. Atomistilor 111, PO Box 53, RO-76900 Bucharest -Magurele (RO) or University Politehnica of Bucharest, Splaiul Independentei 313, Sector 6, RO-77206 Bucharest (RO)Additional details
Identifiers
Publishing Information
- Publisher
- Romanian Nuclear Energy Association, AREN
- Imprint Place
- Bucharest (Romania)
- Imprint Title
- Programme of the International Symposium on Nuclear Energy SIEN 2003, Nuclear Power - A New Challenge
- Imprint Pagination
- 622 p.
- Journal Page Range
- p. 47-55
Conference
- Title
- SIEN 2003, International Symposium on Nuclear Energy, Nuclear Power - A New Challenge
- Dates
- 22-25 Oct 2003
- Place
- Bucharest (Romania)
INIS
- Country of Publication
- Romania
- Country of Input or Organization
- Romania
- INIS RN
- 35046034
- Subject category
- S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS; S29: ENERGY PLANNING, POLICY AND ECONOMY;
- Resource subtype / Literary indicator
- Conference, Non-conventional Literature
- Descriptors DEI
- CAPITALIZED COST; CERNAVODA-1 REACTOR; CONTRACTS; DECISION MAKING; DESIGN; ECONOMIC ANALYSIS; FINANCING; MATHEMATICAL MODELS; PLANNING
- Descriptors DEC
- CANDU TYPE REACTORS; COST; ECONOMICS; HEAVY WATER COOLED REACTORS; HEAVY WATER MODERATED REACTORS; NATURAL URANIUM REACTORS; PHWR TYPE REACTORS; POWER REACTORS; PRESSURE TUBE REACTORS; REACTORS; THERMAL REACTORS
Optional Information
- Notes
- 4 refs., 6 tabs.