Published June 2017 | Version v1
Book

Human factors case study: An iterative approach to verifying and validating a new suite of reactor inspection and maintenance tooling - 177

  • 1. Candesco - Division of Kinectrics, Toronto, Ontario (Canada)
  • 2. Bruce Power, Tiverton, Ontario (Canada)

Description

An iterative approach was taken to perform the HF Verification and Validation (V and V) activities for a complex set of reactor inspection and maintenance tooling equipment known as the Bruce Reactor Inspection and Maintenance System (BRIMS). This paper is divided into the verification activities (of Human System Information Task Support and Design verifications) and the validation activities. The validation method used a graded approach by breaking validation activities into early usability testing and high fidelity validations. Early usability testing, allowed for issues and design concepts to be identified and explored. High fidelity validation activities tested that the final design requirements and operational goals of the system were met in the production equipment. The validation method has been described in detail by depicting the following: task selection criteria, tools, performance measures and data collection. Validation results demonstrate the benefits of the graded approach as issues were to be identified early in the design process, improvements were made during detailed design and additional testing could confirm that issues were resolved prior to commissioning. To capture and share the success of this iterative V and V approach lessons learned have been created for use in future V and V projects. (authors)

Additional details

Publishing Information

Publisher
American Nuclear Society - ANS
Imprint Place
La Grange Park, IL (United States)
Imprint Pagination
11 p.

Conference

Title
10. International Conference on Nuclear Plant Instrumentation, Control, and Human-Machine Interface Technologies
Acronym
NPIC and HIMIT 2017
Dates
11-15 Jun 2017
Place
San Francisco, CA (United States)

Optional Information

Notes
4 refs.; available from American Nuclear Society - ANS, 555 North Kensington Avenue, La Grange Park, IL 60526 (US)