Kori 1 SBO and maintenance rule in Korea
Description
On February 9, 2012, during the 29th refueling outage of Kori 1 nuclear power plant, a station blackout (SBO) occurred and the event was not reported for a long time. By reviewing the Kori 1 SBO event, we are trying to find a necessary system or process to prevent the similar event in this paper. One of reason of the SBO event is the lack of a configuration control including a safer outage work scheduling. It is discussed here why the configuration control is not working even though it is known that the maintenance rule (MRule) is adopted in KHNP. After the SBO event, two main actions were taken by KHNP and NSSC(Nuclear Safety and Security Commission); 1) extended overhaul period and 2) evaluation of outage work schedule by regulatory body. It is also discussed in this paper how these two actions can be performed
Additional details
Publishing Information
- Publisher
- KNS
- Imprint Place
- Daejeon (Korea, Republic of)
- Imprint Title
- Proceedings of the KNS autumn meeting
- Imprint Pagination
- [1 CD-ROM]
- Journal Page Range
- [2 p.]
Conference
- Title
- 2012 autumn meeting of the KNS
- Dates
- 24-26 Oct 2012
- Place
- Kyoungju (Korea, Republic of)
INIS
- Country of Publication
- Korea, Republic of
- Country of Input or Organization
- Korea, Republic of
- INIS RN
- 44062848
- Subject category
- S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
- Resource subtype / Literary indicator
- Conference, Non-conventional Literature
- Descriptors DEI
- CONTROL; KORI-1 REACTOR; MAINTENANCE; OUTAGES; REGULATIONS; REPUBLIC OF KOREA
- Descriptors DEC
- ASIA; DEVELOPING COUNTRIES; ENRICHED URANIUM REACTORS; LAWS; POWER REACTORS; PWR TYPE REACTORS; REACTORS; THERMAL REACTORS; WATER COOLED REACTORS; WATER MODERATED REACTORS
Optional Information
- Notes
- 4 refs, 3 figs