Results of 1-MW operation in J-PARC 3 GeV rapid cycling synchrotron

  • 1. Japan Atomic Energy Agency (JAEA), J-PARC Center, Tokai, Ibaraki (Japan)
  • 2. High Energy Accelerator Research Organization (KEK), J-PARC Center, Tokai, Ibaraki (Japan)

Description

The J-PARC 3 GeV Rapid Cycling Synchrotron (RCS) is aiming to provide the proton beam of very high power for neutron experiments and the main ring synchrotron. We have continued the beam commissioning and the output power from RCS have been increasing. In recent years, just before the summer shutdown period, we have been trying continuous supply of 1-MW high-intensity beam, which is the design value, to a neutron target. First trial was 1-hour continuous operation in July 2018, and second trial was 10-hours continuous in July 2019. In both cases, we achieved almost stable operation. Furthermore, in June 2020, we tried to operate continuously for over 40 hours. But in this case, some trouble occurred and the operation was frequently suspended. Through these continuous operation trials, we have identified issues for stable operation of 1 MW. In this presentation, we will report the results of 1-MW continuous operation and issues obtained from these results. (author)

Availability note (English)

Available from https://www.pasj.jp/web_publish/pasj2020/proceedings/PDF/WEPP/WEPP03.pdf
Part of:
Proceedings of the 17th annual meeting of Particle Accelerator Society of Japan

Additional details

Additional titles

Original title (Japanese)
J-PARC 3GeVシンクロトロン1MW運転状況

Publishing Information

Imprint Title
Proceedings of the 17th annual meeting of Particle Accelerator Society of Japan
Imprint Pagination
[971 p.]
Journal Page Range
p. 209-213

Conference

Title
17. annual meeting of Particle Accelerator Society of Japan
Acronym
PASJ2020
Dates
2-4 Sep 2020
Place
Japan (Japan)

Optional Information

Notes
8 refs., 8 figs. Imprint:This symposium was hold online;#7B2C#17#56DE# #65E5##672C##52A0##901F##5668##5B66##4F1A##5E74##4F1A#