Published 1977 | Version v1
Miscellaneous Restricted

Routine testing on protective and safety systems and components

Creators

  • 1. Kraftwerk Union A.G., Erlangen (Germany, F.R.)

Description

1) In-process inspection, tests during commissioning. 2) Tests during reactor operation. 2.1) Reactor protection system, for example: continuous auto-testing by a dynamic system, check of the output signals; 2.2) safety features: selected examples: functional tests on the ECCS, trial operation of the emergency diesels. 3) Tests during refuelling phase. 3.1) Containment: Leakage rate tests, leak testing; 3.2) coolant system: selected examples: inservice inspections of the pressure vessel, eddy current testing of the steam generator, functional tests of safety valves. (orig./HP)

Availability note (English)

MF available from INIS under the Report Number.

Abstract (German)

1) Pruefungen waehrend der Herstellung, Pruefungen waehrend der Inbetriebnahme. 2) Pruefungen waehrend des Reaktorbetriebs. 2.1) Reaktorschutzsystem z.B.: kontinuierliche Selbstueberwachung durch ein dynamisches System, Ueberpruefung der Ausgangssignale; 2.2) Sicherheitseinrichtungen: ausgewaehlte Beispiele: Funktionspruefungen am Kernnotkuehlsystem, Probebetrieb der Notstromdiesel. 3) Pruefungen waehrend des Stillstands zum BE-Wechsel. 3.1) Leckratenpruefung an der Sicherheitshuelle, Lecksuche; 3.2) Primaerkuehlkreislauf: ausgewaehlte Beispiele: Wiederholungspruefung am Druckbehaelter, Wirbelstrompruefung am Dampferzeuger, Funktionspruefungen der Sicherheitsventile. (orig./HP)

Files

Restricted

The record is publicly accessible, but files are restricted to users with access.

Additional details

Publishing Information

Imprint Pagination
48 p.
Report number
AED-Conf--77-498-071

Conference

Title
IAEA interregional training course on construction and operation management of a nuclear power plant.
Dates
5 Sep - 25 Nov 1977.
Place
Karlsruhe, Germany, F.R.

Optional Information

Notes
22 figs.; with refs.