[en] The no. 2 uranium plant at Western Deep Levels gold mine which recently came into operation, was designed to process 200 000 t of material per month. The plant is capable of treating ore straight from the mine and also an existing tailings dump. The earthworks, civil works and critical dates during the construction are discussed, as well as the construction management and construction programme