AbstractAbstract
[en] 32 wind power plants, 50-300 kW, are included in this survey of availability, capacity factors, energy production and operational disturbances. Some results: Mean availability has been above 0.95, mean capacity factor 0.2. The investment cost is around 8000 SEK/kW (about 1400 USD/kW). The best installations can be profitable if electricity tax relief is granted. Most disturbances originate in the control systems, the generators and the yaw systems. (13 figs., 10 tabs.)
Original Title
Driftuppfoeljning av smaa och medelstora vindkraftverk 1989-1991
Primary Subject
Source
Sep 1992; 48 p; OSTI as DE93500836; NTIS; INIS; Also available from: Vattenfall AB, Research Vindenergi, attn. Anders Andersson, Box 88, S-620 20 Klintehamn, Sweden